Abstract

The collapse zone formed on the earth’s surface over underground mines is a territory excluded from economic activity. Depending on the size of a mine, this zone can be considerable, with an area of up to hundreds of thousands square meters. It is possible to dump overburden and other mining wastes on this territory taking into account the necessary safety measures for the relevant technological processes. The paper proposes solutions for dumping hard overburden rocks from an open pit in the collapse zone over the existing underground mine. The decisions are aimed at the safety of operations in the hazardous zone. The measures are aimed at the implementation of two tasks: stability of the dump body on the weak base, which is composed of clay sedimentary rocks and disturbed by sinks; safety of personnel and equipment in the collapse zone. To solve the first problem, the stability parameters of the overburden dump are determined. The calculations were performed by two methods: finite element modeling and limit equilibrium. To solve the second problem connected with safety of personnel in the collapse zone, the sinking termination criterion defined as the maximum volume achievable by a sink is developed. The final volume of a sink is determined by the mined-out void size, mining depth and by the parameters of rocks in the collapse zone. The actual volume of the sinks is measured using geodetic methods (UAV survey, laser scanning) The separation of the technological process into the advanced filling of sinks and segmented dump formation is proposed. The sink filling should begin when the sinking termination criterion is met. The formation of the dump should be carried out in segments, in the prepared areas with the filled sinks. Planning and segmentation of dumping operations is carried out in accordance with the schedule of underground work; no personnel or operation are allowed over active extraction blocks.

keywords Sink, sinking termination, deformation monitoring, waste dump, stability analysis, finite element method, swell factor
References

1. Usanov S. V., Krutikov A. V., Melnik D. E. Ensuring of industrial safety when developing Sokolovskiy iron-ore deposit by underground method in terms of flooded overlapping strata. Problemy nedropolzovaniya. 2018. No. 4. pp. 82–89.
2. Russkiy I. I. Dumping in open pit mining. 2nd enlarged and revised edition. Moscow : Nedra, 1971. 240 p.
3. Shnayder M. F., Voronenko B. K. Combination of underground and open-cast mining of ore deposits. Moscow : Nedra, 1985. 132 p.
4. Artkhonghan K., Sartkaew S., Thongprapha T., Fuenkajorn K. Effects of stress path on shear strength of a rock salt. International Journal of Rock Mechanics and Mining Sciences. 2018. Vol. 104. pp. 78–83.
5. I-Hsuan Ho. Parametric studies of slope stability analyses using three-dimensional finite element technique: geometric effect. Journal of GeoEngineering. 2014. Vol. 9, No. 1. pp. 33–43.
6. Peng Wu, Haoshuai Wu, Yanlong Chen. Simulation Accuracy Analysis of Slope Stability Based on Finite Element Shear Strength Reduction (SSR) Method. International Journal of Mining Science. 2017. Vol. 3, Iss. 3. pp. 52–59.
7. Fisenko G. L. Stability of pit and dump edges. 2nd enlarged and revised edition. Moscow : Nedra, 1965. 378 p.
8. Huang Y. H. Stability Analysis of Earth Slopes. New York : Van Nostrand Reinhold Company Inc., 1983. 305 p.
9. Fedorovskiy V. G., Kurillo S. V. Slope stability design technique. Geoekologiya. Inzhenernaya geologiya. Gidrogeologiya. Geokriologiya. 1997. No. 6. pp. 95–106.
10. Kazikaev D. M. Geomechanical processes in the time of joint and repeated ore mining. Moscow : Nedra, 1981. 288 p.
11. Galchenko Yu. P., Eremenko V. A., Myaskov A. V., Kosyreva M. A. Solution of geoecological problems in underground mining of deep iron ore deposits. Eurasian Mining. 2018. No. 1. pp. 35–40. DOI: 10.17580/em.2018.01.08
12. Anikeev A. V. Sinks and subsidence craters in the karst areas: mechanisms, prediction and risk assessment. Moscow : RUDN, 2017. 328 p.
13. Lan Cui, Qian Sheng, Jun-jie Zheng, Zhen Cui, An Wang, Qiang Shen. Regression model for predicting tunnel strain in strain-softening rock massfor underground openings. International Journal of Rock Mechanics and Mining Sciences. 2019. Vol. 119. pp. 81–97.
14. Efremov E. Yu. Rationale of cave-in process consummation criterion. Izvestiya Tulskogo gosudarstvennogo universiteta. Nauki o Zemle. 2018. No. 4. pp. 12–21.
15. Sannikova A. P., Bazykina L. R., Ozhigin D. S. Methodology for effective determination of rock jointing in calculation of open pit edges. Journal of Industrial Pollution Control. 2017. Vol. 33, No. 1. pp. 852–855.
16. Dorokhov D. V., Nizametdinov F. K., Ozhigin S. G., Ozhigina S. B. A technique for surveying of ground surface deformations in mine field. Journal of Mining Science. 2018. Vol. 54, Iss. 5. pp. 874–882
17. Lucieer A., de Jong S. M., Turner D. Mapping landslide displacements using Structure from Motion (SfM) and image correlation of multi-temporal UAV photography. Progress in Physical Geography: Earth and Environment. 2014. Vol. 38, Iss. 1. pp. 97–116.

Language of full-text russian
Full content Buy
Back